NERC CIP audit preparation: a 90-day plan

Your Regional Entity's audit notice gives you about 90 days. A week-by-week plan to prepare evidence, close gaps, brief your subject matter experts and answer the RSAW and RFIs with confidence.

· 8 min read · CIP Sentry

Regional Entities send a compliance audit notice at least 90 days before the audit. That notice lists the standards in scope, the audit period and the initial Requests for Information (RFIs). Ninety days sounds like a lot until you start chasing evidence from three years ago. Here is a plan.

Days 1–10: scope and organize

Days 11–40: gather and test evidence

Days 41–60: close gaps honestly

If you find a possible violation, don’t hide it. Talk to your compliance and legal leads about self-reporting or self-logging through your Regional Entity’s process. Self-identified issues with prompt mitigation are treated far better than issues found by auditors. Meanwhile, fix the underlying process so the gap doesn’t recur.

Days 61–80: prepare people

Days 81–90: submit and stay calm

Submit RFI responses on time, clearly labeled and indexed to requirement parts. Keep a log of every request and response during the audit. After the audit, capture lessons learned while they’re fresh.

The real lesson

Audit preparation is easy when evidence is created as the work happens and stored against the requirement it proves. It is painful when evidence has to be reconstructed. The best time to prepare for your next audit is the day after this one ends.


Want a quick read on where you stand? Take the free NERC CIP audit readiness self-assessment. CIP Sentry’s Audit Center keeps a requirement catalog, evidence vault, audit trail and 51 ready-made reports in one place. Request a quote.

Request a quote

See CIP Sentry on your own terms.

Get a quote sized to your registered functions and impact levels, and a live walkthrough on sample data. No sales pressure, no cloud account, no commitment.